PERT Chart
Estimate, Schedule, and Control a network of interdependent tasks
Shown by arrows, nodes, or circles
Program, Evaluation and Renew Technique
Determine minimum time needed to complete a project, phase, or task
Critical Path
- Minimum time needed to complete a project or phase
- Total of the most time-consuming chain of events
Four Steps
- Identify Tasks
- Determine Proper Sequence of Tasks
- Estimate the Time Required to Perform each Task
- Prepare Time-Scaled Chart of Tasks and Events to Determine the Critical Path